Question
1 Approved Answer
Question 1 0.1 pts If an activity duration cannot be estimated accurately, we should Use the average estimate in our critical path method 0 Use
Question 1 0.1 pts If an activity duration cannot be estimated accurately, we should Use the average estimate in our critical path method 0 Use the worst case estimate in our critical path method Move away from single point estimates and rely on 2 point (best and worst case) estimates Move away from single point estimates and rely on a 3 point (best, worst and most likely case) estimates