Question

1 Approved Answer

Question 2: 50 points total Part 1: ( See figure 2 part 1 below ). Calculate the ES, EF, LS, and LF times and the

Question 2: 50 points total

Part 1: (See figure 2 part 1 below). Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project (MUST SHOW WORK TO GET CREDIT INCLUDE FORMULAS). Can the project be completed in the required completion time of 38 weeks? Why or why not? (25 points)

Part 2: (See figure 2 part 2 below). Assume that Systems Analysis actually finished (duration) at 7 weeks, Design Input & Output actually finished (duration) at 3 weeks, and Develop Output Reports actually finished (duration) at 8 weeks. Can the project be completed in the required completion time of 38 weeks? Why or why not? (25 pts)

image text in transcribed

Part 1: Table for Part 1

Activity # Activity ES EF LS LF Total Slack
1 Problem Definition
2 System Analysis
3 Design Input & Output
4 Design Database
5 Developer Input Screens
6 Develop Output Reports
7 Develop Database
8 Test System
9 Implement System

EF=ES+ Estimated Duration

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective small business management An Entrepreneurial Approach

Authors: Norman M. Scarborough

10th Edition

132157462, 978-0132157469

More Books

Students also viewed these General Management questions