Question 3 What are some tactics to handle external scope creep? Select all that apply. 1 point Limit communication outside the team once the project
Question
What are some tactics to handle external scope creep? Select all that apply.
point
Limit communication outside the team once the project begins
Define the projects requirements.
Tell team members to ignore outside requests that will add project tasks.
Suggest alternative solutions to your customer's or stakeholder's proposed changes.