Question

1 Approved Answer

Reference the preliminary project schedule (see figure below), answer the following questions. NOTE: The critical path of this project comprises of Tasks 3, 4 and

Reference the preliminary project schedule (see figure below), answer the following questions.

image text in transcribed

NOTE: The critical path of this project comprises of Tasks 3, 4 and 6.

Question 1: Perform resource leveling for this project (without delaying the project). How many workers would you need?

Question 2: Using the smallest-slack-first rule, perform a resource-constrained leveling of the project for a scenario where only three workers are available to work on this project. What is the new project completion date?

Instructions: You can copy/paste the grid multiple times to document each iteration of the resource leveling heuristic. Add rows and columns as needed. You are free to use another format to do this assignment, if you like. Crtitical Path is 3-4-6 Instructions: You can copy/paste the grid multiple times to document each iteration of the resource leveling heuristic. Add rows and columns as needed. You are free to use another format to do this assignment, if you like.

Crtitical Path is 3-4-6
TASK 1 2 2 2 2
TASK 2 1 1 1
TASK 3 3 3 3
TASK 4 2 2 2 2
TASK 5 1 1 1
TASK 6 3 3 3
Day 1 2 3 4 5 6 7 8 9 10
Workers 6 6 6 4 2 3 3 4 3 3

instructions: You can copy/paste the grid multiple times to document each iteration of the resource leveling heuristic. Add rows and columns as needed. You are free to use another format to do this assignment, if you like

Crtitical Path is 3-4-6
Slack
TASK 1 2 2 2 2 6
TASK 2 1 1 1 7
TASK 3 3 3 3 0 Because it is a critical task
TASK 4 2 2 2 2 0 Because it is a critical task
TASK 5 1 1 1 2
TASK 6 3 3 3 0 Because it is a critical task
Day 1 2 3 4 5 6 7 8 9 10
Workers 6 6 6 4 2 3 3 4 3 3
Use smallest slack first heurtistic

Submit using an Excel document

\begin{tabular}{|c|c|c|c|c|c|c|c|c|c|c|} \hline & & 1 & vor & & & & & & & T \\ \hline & Task & (1 & orke & & & & & & & \\ \hline & Task & (3 & orke & & & & & | & & 1 \\ \hline & & & & & & & & & & 1 \\ \hline & & & & & 4 & wor & & & & 1 \\ \hline & & & & & & Tas & (1 & orker & & | \\ \hline & & & & & & & & Task & (3 & grkers) \\ \hline & & & & & & & & & & \\ \hline Day & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & 9 & 10 \\ \hline Workers & 6 & 6 & 6 & 4 & 2 & 3 & 3 & 4 & 3 & 3 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Supply Chain and Operations An Integrative Approach

Authors: Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W Webb

1st edition

132832402, 978-0132832403

More Books

Students also viewed these General Management questions