Question: Referring to the resource load chart from question # 1 4 , assume these have six programmers rather than five. Which activit ( ies )

Referring to the resource load chart from question #14, assume these have six programmers rather than five. Which activit(ies) should be committed to the schedule that day? Question 15 options: Activity #5(load testing) only Activities #5(load testing) and #6(use case testing) Activities #5(load testing) and #4(compatibility testing) Activities #4(compatibility testing), #5(load testing), and #6(use case testing)