Question
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road
Required information
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,581,000 | $ | 2,347,000 | $ | 3,049,200 | |||
Estimated costs to complete as of year-end | 6,319,000 | 2,772,000 | 0 | ||||||
Billings during the year | 2,090,000 | 2,838,000 | 5,072,000 | ||||||
Cash collections during the year | 1,845,000 | 2,900,000 | 5,255,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started