Question: Section B: Short Answer Questions Anster ALL the questions. (5 questions x 3 marks = 15 marks) Bl. Use the following information in the activities
Section B: Short Answer Questions Anster ALL the questions. (5 questions x 3 marks = 15 marks) Bl. Use the following information in the activities table of an information technology project for XYZ Hospital and draw a Gantt chart for the project. Activity Dependencies Duration Activity Predecessors (days) A 3 4 2 Fc n EF D A B B, C DE 1 3 B2. Create a CRUD Matrix for the following Activities. 1) Place an order 2) Assemble an order 3) Ship order 4) Close Order Activities Customers Order Products B3. 1 Is risk management being important for a project? Justify your answer. ii. List any three activities involved in the risk management