Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Sequence the jobs shown by using a Gantt chart. Assume that the move time between machines is one hour. Also, assume there are two machines

Sequence the jobs shown by using a Gantt chart. Assume that the move time between machines is one hour. Also, assume there are two machines of type A, two of type B, and two of type C. Sequence the jobs in priority order 1,2,3,4.
Job Work Center/Machine Hours Due Date (days)
1 A/3, B/2, C/23
2 C/2, A/42
3 B/6, A/1, C/34
4 C/4, A/1, B/23
Prepare a finite capacity schedule.
a. What is the makespan?
b. How much machine idle time is there?
c. When is each job delivered compared with its due date?
d. How much idle time (waiting time) is there for each job?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Short Term Financial Management

Authors: John Zietlow, Matthew Hill, Terry Maness

5th Edition

1516512405, 9781516512409

More Books

Students also viewed these Finance questions