7. (10pts) Use Johnson's Rule to determine the optimum processing sequence for the jobs listed below. Processing Time (minutes) Center 1 20 B 8


7. (10pts) Use Johnson's Rule to determine the optimum processing sequence for the jobs listed below. Processing Time (minutes) Center 1 20 B 8 42 IT X 2 D 14 E Zb 18 A F Center 2 12 32 8 7-3 Y 7 6 a) Determine the values of X, Y and Z as positive integers between 5 and 35 in the following table. 68.6 X Y 7 14 b) Based on the values of X, Y and Z in part a). what is the optimum processing sequence? Construct a time-phased chart. What is the throughput time of the system? What are the idle times for the two centers? 2% X 8 88 16 20 36 14 36 18 Z 7 21 6 BE

Step by Step Solution

3.36 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Mathematics For Business Economics, Life Sciences, And Social Sciences

Authors: Raymond Barnett, Michael Ziegler, Karl Byleen, Christopher Stocker

14th Edition

0134674146, 978-0134674148

More Books

Students also viewed these Mathematics questions

Question

What are the benefits of making a to-do list? (p. 299)

Answered: 1 week ago

Question

What is the data type of an item that stores a pre defined list?

Answered: 1 week ago

Question

Summarize current research on the heritability of personality.

Answered: 1 week ago