Task Predecessors Tasks (Dependencies) Time (Weeks A 0 3 B 0 5 C 0 7 D A 7 E B 5 F C 5 G
Task | Predecessors Tasks (Dependencies) | Time (Weeks | ||||||||
A | 0 | 3 | ||||||||
B | 0 | 5 | ||||||||
C | 0 | 7 | ||||||||
D | A | 7 | ||||||||
E | B | 5 | ||||||||
F | C | 5 | ||||||||
G | E | 4 | ||||||||
H | F | 5 | ||||||||
I | D | 6 | ||||||||
J | G,H,I | 4 | ||||||||
Create an AON (Activity on Node) Pert Diagram given the information in the table above. Be sure to identify the slack time for each activity | ||||||||||
Identify the project's critical path | ||||||||||
What is the significance of being able to identify critical path? | ||||||||||
Discuss any three points that will demonstrate the importance of project management to organizations in Jamaica. | ||||||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started