The critical path for the network activities shown below is _ _ _ _ _ with duration _ _ _ _ _ _ . Activity

The critical path for the network activities shown below is _____ with duration ______.Activity Duration Immediate A 4---B 2 AC 7--D 4 AE 5 B,C,Da.A-D-E; 13b.A-B-D; 10