Question
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company:
Activity Center | Variable | Fixed | Cost Driver |
Statement inquiry | $76,164 | $161,000 | 3,300 labor hours |
Correspondence | $10,092 | $22,000 | 2,900 letters |
Account billing | $147,000 | $72,000 | 2,450,000 lines |
Payment verification | $9,165 | $76,000 | 19,500 accounts |
In September, actual total costs and activity were as follows:
Activity Center | Total Costs | Driver Amount |
Statement inquiry | $232,981 | 3,160 labor hours |
Correspondence | $32,773 | 3,090 letters |
Account billing | $215,581 | 2,390,000 lines |
Payment verification | $84,438 | 19,640 accounts |
Required Compute the flexible-budget variances for the following two activity cost items (round unit costs to two decimal places and enter favorable variances as positive numbers and unfavorable variances as negative numbers): Payment verification : Account billing :
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started