The following represents a project with four activities. All times are in weeks. Immediate Predecessor ime Optimistic Most Likely Pessimistic Time 14 Activity Time


The following represents a project with four activities. All times are in weeks. Immediate Predecessor ime Optimistic Most Likely Pessimistic Time 14 Activity Time A 18 17 15 11 According to the table, what is the critical path? Oa BD OBAB Oc AC Od'ABCD

Step by Step Solution

3.45 Rating (155 Votes )

There are 3 Steps involved in it

Step: 1

EXPECTED TIME FORMULA a 4m b 6 A 2 4 8 14 6 8 B 8 4 8 8 6 8 C 6 4 9 18 6 10 D 5 4 11 17 6 11 VARIANC... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations And Supply Chain Management

Authors: F. Robert Jacobs, Richard Chase

14th Edition

978-0077824921, 78024021, 9780077823344, 007782492X, 77823346, 978-0078024023

More Books

Students also viewed these Accounting questions