The following table contains information about four jobs that are waiting for processing at a machine. Job Job Time (days) Due Date (days) A 14

The following table contains information about four jobs that are waiting for processing at a machine.

Job Job Time (days) Due Date (days)
A 14 20
B 10 16
C 7 15
D 6 17

Apply the SPT rule to sequence the jobs and answer questions 1 to 6.

Q1: 1stjob in the sequence will be:

  1. Option A
  2. Option B
  3. Option C
  4. Option D

Q2: 2ndjob in the sequence will be:

  1. Option A
  2. Option B
  3. Option C
  4. Option D

Q3: 3rdjob in the sequence will be:

  1. Option A
  2. Option B
  3. Option C
  4. Option D

Q4: What will be the average flow time with the SPT sequence? (Round to 2 decimal places)

Q5: What will be the average Work in Progress with SPT sequence? (Round to 2 decimal places)

Q6. What will be the average lateness with SPT sequence?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Emma Bell, Bill Harley, Alan Bryman

6th Edition

0198869444, 9780198869443

More Books

Students also viewed these General Management questions