The following table contains information about four jobs that are waiting for processing at a machine. Job Job Time (days) Due Date (days) A 14
The following table contains information about four jobs that are waiting for processing at a machine.
Job | Job Time (days) | Due Date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Apply the SPT rule to sequence the jobs and answer questions 1 to 6.
Q1: 1stjob in the sequence will be:
- Option A
- Option B
- Option C
- Option D
Q2: 2ndjob in the sequence will be:
- Option A
- Option B
- Option C
- Option D
Q3: 3rdjob in the sequence will be:
- Option A
- Option B
- Option C
- Option D
Q4: What will be the average flow time with the SPT sequence? (Round to 2 decimal places)
Q5: What will be the average Work in Progress with SPT sequence? (Round to 2 decimal places)
Q6. What will be the average lateness with SPT sequence?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started