The table below provides cost and time estimates of seven activities of a project. Activity Time estimates Direct cost (weeks) estimates(kwacha, in thousands Normal Crash

The table below provides cost and time estimates of seven activities of a project.

image text in transcribed
Activity Time estimates Direct cost (weeks) estimates(kwacha, in thousands Normal Crash Normal Crash (1,2) 2 10 (1, 3 ) 1 15 8 5 15 ( 2, 4 ) 21 4 3 20 24 (3, 4) 1 7 7 (3, 5) 2 1 8 (4, 6) 5 15 3 (5,6) 6 10 16 2 12 36 (i) Draw the project network corresponding to normal (ii ) time. Determine the critical path and the normal duration and normal cost of the project. TAILOKA FRANK PATSON OPERATIONS RESEARCH ACADEMIC YEAR 2020 10 (iii) Crash the activities so that the project completion time reduces to 9 weeks, with minimum additional cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Internet Supply Chain Impact On Accounting And Logistics

Authors: D. Chorafas

5th Edition

0333949633, 9780333949634

More Books

Students also viewed these Accounting questions

Question

Explain demotion as an alternative to termination.

Answered: 1 week ago

Question

Discuss termination of employees at various levels.

Answered: 1 week ago

Question

Discuss the various approaches to disciplinary action.

Answered: 1 week ago