A project was estimated to cost $ 200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly delayed. This

image text in transcribed

image text in transcribed

A project was estimated to cost $ 200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly delayed. This was however made up by receiving the first batch of materials for the project by air. The net result was that there was some additional cost in the project. At the end of the second month, the Project Manager reviews the project and finds that the project is 20% complete and Actual Costs are $ 50,000. The Estimate to complete (ETC) for the project would now be: A. $160,000 B. $210,000 C. $250,000 D. $200,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems

Authors: Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill

11th edition

1337552127, 978-1305971424, 1305971426, 978-0357688694, 978-1337673174, 133767317X, 978-1337552127

More Books

Students also viewed these Accounting questions

Question

6. Talk among students, such as giving help or socializing

Answered: 1 week ago