Given the following project network: a. Identify the critical path. A-B-D-F A-C-E-F A-C-D-F b. Identify the early start for task D. c. Identify the late
Given the following project network: a. Identify the critical path. A-B-D-F A-C-E-F A-C-D-F b. Identify the early start for task D. c. Identify the late finish for task C. d. Calculate slack for task E