Question
Use Cases were identified for the RTGM in Chapter 5 ( see Figure 11-23) . Additional Descriptions of the system requirements are found in Chapters
Use Cases were identified for the RTGM in Chapter 5 (see Figure 11-23). Additional Descriptions of the system requirements are found in Chapters 3, 4, and 8. You might want to refresh your memory of the needs for this system.
Figure 11-23
Complete these tasks:
Based on the use case diagram and other project information, develop a list of software components (subsystems) that must be acquired or developed. Describe the function(s) of each component in detail. Be sure to consider components thatarent directly tied to use cases, such as the software interface between glucose monitoring wristband and the cell phone.
List of Software Components Example
Subsystem | Use cases |
Prioritize the list of software components based on risk.
Prepare a project iteration schedule based on iterations that last between two and four weeks. The schedule should include all the tasks needed to develop a complete version of the system, which will then be subjected to live testing andevaluation by real users for three months.
Project Iteration Schedule Example
Iteration | Subsystem | Use case |
#1 | ||
#2 | ||
#3 | ||
#4 | ||
#5 | ||
#6 | ||
#7 | ||
#8 | ||
#9 |
Prepare a detailed work schedule for the first iteration. Since you have access to project management software prepare:
the work schedule
a Gantt chart by using the software.
Work Schedule Example
Discipline | Activity | Effort | Dependency |
Planning | |||
Analysis Activities | |||
Design Activities | |||
Build Activities | |||
Total Days |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started