Answered step by step
Verified Expert Solution
Question
1 Approved Answer
What is an accurate difference between the Program Evaluation and Review Technique ( PERT ) and critical path method ( CPM ) ? a .
What is an accurate difference between the Program Evaluation and Review Technique PERT and critical path method CPM
a CPM involves more work than PERT because it requires several duration estimates.
b CPM addresses the risk associated with duration estimates whereas PERT does not.
c Unlike CPM PERT estimates only when there is no risk of uncertainty.
d PERT uses different duration estimates whereas CPM uses one specific duration estimate.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started