What is the meaning of a schedule performance Index (SPI) of 0.85? A: Schedule performance is unfavorable indicating less work is being accomplished than planned.
What is the meaning of a schedule performance Index (SPI) of 0.85?
A: Schedule performance is unfavorable indicating less work is being accomplished than planned.
B: Schedule performance is favorable indicating more work is being accomplished than planned.
C: There is no way to interpret the SPI without also looking at the cost performance index (CPI)
D: Schedule performance is as efficient as planned