When a priority rated order is placed, the contractor must do all of the following tasks EXCEPT A. Provide preferential performance as needed to meet
When a priority rated order is placed, the contractor must do all of the following tasks EXCEPT A. Provide preferential performance as needed to meet program delivery requirements B. Accept the rated order if the material or service is normally supplied C. Place rated orders with subcontractors or suppliers D. Deliver the specified end product within 10 business days