Which of the following is not a measure for judging the effectiveness of a schedule sequence? Multiple Choice average number of jobs at the work
Which of the following is not a measure for judging the effectiveness of a schedule sequence?
Multiple Choice
average number of jobs at the work center
total number of jobs at the work center
average completion flow time
average job tardiness
length of time between start of first job to completion of the last job in the work center