Which of the following statements, if any, concerning the earned value variable of budgeted cost for work performed (BCWP) is incorrect? None of the statements
Which of the following statements, if any, concerning the earned value variable of budgeted cost for work performed (BCWP) is incorrect?
None of the statements is correct.
BCWP is a measure of work progress, while ACWP reflects actual costs such as for labor and material.
The value for the BCWP reflects completed work stated in terms the work?s BCWS.
BCWP and BCWS for a given work scope are unrelated.
BCWP is also called ? earned value?