Question

1 Approved Answer

Which one of the following is NOT a proper distribution of the risk driver technique for project risk simulation? The risk driver accounts for the

Which one of the following is NOT a proper distribution of the risk driver technique for project risk simulation? The risk driver accounts for the possible effects of individual risk factors on project objectives. The risk driver accounts for the probability of occurrence of individual risk factors. The risk driver cannot be applied concurrently to both time and cost of an activity. Risk drivers often represent the risk events identified in a risk register. None of the others

Step by Step Solution

3.29 Rating (155 Votes )

There are 3 Steps involved in it

Step: 1

The detailed answer for the above question is provided below The statement The risk driver cannot be ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting concepts and applications

Authors: Albrecht Stice, Stice Swain

11th Edition

978-0538750196, 538745487, 538750197, 978-0538745482

More Books

Students also viewed these Accounting questions

Question

List the three solutions for developing a more playful attitude.

Answered: 1 week ago

Question

Distinguish between hyperstress and distress.

Answered: 1 week ago