Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are a project manager hired to manage construction of an amphitheather on the Foothill College campus. Use the data found in Table 1 below

You are a project manager hired to manage construction of an amphitheather on the Foothill College campus. Use the data found in Table 1 below to draw a PERT diagram that you can use to answer the questions below.

image text in transcribed

Which of the following is NOT a feasible path through the PERT Diagram

A.

BEK

B.

ADK

C.

JK

D.

CHI

E.

CEK

Which of the following is the CRITICAL PATH

A.

CHI

B.

BEK

C.

JK

D.

ADK

E.

CEK

According to the CRITICAL PATH, how long will the project take to complete?

A.

15 weeks

B.

51 weeks

C.

19 weeks

D.

6 weeks

E.

32 weeks

If the time to complete Activity B increases by 1 week and the time to complete Activity I decreases by 1 week, what happens to the project's overall time to complete?

A.

The overall time to complete increases by 2 weeks

B.

The overall time to complete remains unchanged

C.

The overall time to complete decreases by 2 weeks

D.

The overall time to compete increases by 1 week

E.

The overall time to complete decreases by 1 week

TABLE 1 \begin{tabular}{|c|c|c|} \hline Activity & Predecessor & Duration(weeks) \\ \hline A & -- & 6 \\ \hline B & -- & 4 \\ \hline C & -- & 5 \\ \hline D & A & 7 \\ \hline E & B & 4 \\ \hline F & B & 4 \\ \hline G & C & 5 \\ \hline H & C & 6 \\ \hline I & G,H & 4 \\ \hline J & - & 5 \\ \hline K & D, E, J & 1 \\ \hline \end{tabular} TABLE 1 \begin{tabular}{|c|c|c|} \hline Activity & Predecessor & Duration(weeks) \\ \hline A & -- & 6 \\ \hline B & -- & 4 \\ \hline C & -- & 5 \\ \hline D & A & 7 \\ \hline E & B & 4 \\ \hline F & B & 4 \\ \hline G & C & 5 \\ \hline H & C & 6 \\ \hline I & G,H & 4 \\ \hline J & - & 5 \\ \hline K & D, E, J & 1 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MGMT Principles Of Management

Authors: Chuck Williams

11th Edition

133740747X, 9781337407472

More Books

Students also viewed these General Management questions