You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. Activity START A B C D E F G H FINISH Normal Time (days) 0 8 7 3 8 5 8 4 6 0 Normal Cost (S) 0 50 40 70 20 30 80 50 60 D Crash Time (days) 0 7 3 1 6 5 A 1 4 0 Crash Cost ($) Immediate Predecessor(s) 0 180 360 310 100 30 520 320 100 a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is 22 days. (Enter your response as an integer.) b. Suppose the variable overhead costs are $30 per day for your project. Also, suppose that the center must pay $80 per day for a temporary room on day 17 or beyond. Find the minimum-cost project schedule. Fill in the table below to show the proper schedule (time for each activity after crashing) for completing the project at minimum cost. (Enter your responses as integers.) Activity Time (days) Activity Time (days) A 8 E B F D G H L START START B A, C A.C B D E. F G, H E
Step by Step Solution
★★★★★
3.44 Rating (144 Votes )
There are 3 Steps involved in it
Step: 1
Activity A B Time days 8 6 Normal Cost 50 60 Crash Cost 100 80 Crash ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started