You are in the middle of executing a major modification to an existing product when you learn that the resources promised at the beginning of
You are in the middle of executing a major modification to an existing product when you learn that the resources promised at the beginning of the project are not available. The BEST thing to do is to: A. Show how the resources were originally promised to your project B. Replan the project without the resources C. Explain the impact if the promised resources are not made available D. Crash the project
Step by Step Solution
There are 3 Steps involved in it
Step: 1