You are provided with the following information for a project, with activity durations given in days: Activity Immediate Predecessor Optimistic Time (a) Most Likely Time

You are provided with the following information for a project, with activity durations given in days:

Activity Immediate Predecessor Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b)
A --- 3 5 8
B --- 2 4 7
C --- 6 8 11
D A, B 5 7 9
E B, C 3 6 10
F C 4 5 6
G E, F 7 10 12
H D 2 3 4
I E, G, H 10 13 16
J G, I, F 12 15 17
K H 8 11 14

  1. Construct a project network.
  2. Determine the expected times and variances for each activity.
  3. Determine the critical path after you have found ES, EF, LS, LF and Slack. State the path and time the project is expected to take.
  4. What is the probability that the project would be completed within 50 days?
  5. What is the probability that the project would be completed within 54 days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Business Analytics

Authors: Troy Adair

1st Edition

1119132002, 9781119132004

More Books

Students also viewed these Mathematics questions

Question

Is it eyewitness or hearsay evidence?

Answered: 1 week ago