You are provided with the following information for a project, with activity durations given in days: Activity Immediate Predecessor Optimistic Time (a) Most Likely Time
You are provided with the following information for a project, with activity durations given in days:
Activity | Immediate Predecessor | Optimistic Time (a) | Most Likely Time (m) | Pessimistic Time (b) |
A | --- | 3 | 5 | 8 |
B | --- | 2 | 4 | 7 |
C | --- | 6 | 8 | 11 |
D | A, B | 5 | 7 | 9 |
E | B, C | 3 | 6 | 10 |
F | C | 4 | 5 | 6 |
G | E, F | 7 | 10 | 12 |
H | D | 2 | 3 | 4 |
I | E, G, H | 10 | 13 | 16 |
J | G, I, F | 12 | 15 | 17 |
K | H | 8 | 11 | 14 |
- Construct a project network.
- Determine the expected times and variances for each activity.
- Determine the critical path after you have found ES, EF, LS, LF and Slack. State the path and time the project is expected to take.
- What is the probability that the project would be completed within 50 days?
- What is the probability that the project would be completed within 54 days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started