Question

1 Approved Answer

You have been asked to evaluate the economic implications of various methods for cooling condenser effluents from a 200-MW steamelectric plant. There are two basic

You have been asked to evaluate the economic implications of various methods for cooling condenser effluents from a 200-MW steamelectric plant. There are two basic types of cooling towers: wet and dry. Furthermore, heat may be removed from condenser water by (1) forcing (mechanically) air through the tower or (2) allowing heat transfer to occur by making use of natural draft. Consequently, there are four basic cooling tower designs that could be considered. Assuming that the cost of capital to the utility company is 10% per year, your job is to recommend the best alternative (i.e., the least expensive during the service life). Further, assume that each alternative is capable of satisfactorily removing waste heat from the condensers of a 200-MW power plant. What noneconomic factors can you identify that might also play a role in the decision-making process?image text in transcribed

rat Alternative Wet Tower Wet Tower Dry Tower Dry Tower Mech. Draft Natural Draft Mech. Draft Natural Draft Initial cost $3.1 million $9.2 million $5.1 million $8.8 million Power for I.D. fans 40 200-hp 1.D. fans None 20 200-hp I.D. fans None Power for pumps 20 150-hp pumps 20 150-hp pumps 40 100-hp pumps 40 100-hp pumps Mechanical maintenance/year $0.12 million $0.10 million $0.16 million $0.11 million Service life 30 years 30 years 30 years 30 years Market value 100 hp = 74.6 kW; cost of power to plant is 2.2 cents per kWh or kilowatt-hour; induced-draft fans and pumps operate around the clock for 365 days/year (continuously). Assume that electric motors for pumps and fans are 90% efficient. rat Alternative Wet Tower Wet Tower Dry Tower Dry Tower Mech. Draft Natural Draft Mech. Draft Natural Draft Initial cost $3.1 million $9.2 million $5.1 million $8.8 million Power for I.D. fans 40 200-hp 1.D. fans None 20 200-hp I.D. fans None Power for pumps 20 150-hp pumps 20 150-hp pumps 40 100-hp pumps 40 100-hp pumps Mechanical maintenance/year $0.12 million $0.10 million $0.16 million $0.11 million Service life 30 years 30 years 30 years 30 years Market value 100 hp = 74.6 kW; cost of power to plant is 2.2 cents per kWh or kilowatt-hour; induced-draft fans and pumps operate around the clock for 365 days/year (continuously). Assume that electric motors for pumps and fans are 90% efficient

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Bitcoin

Authors: Robert P. Murphy ,Silas Barta

1st Edition

1505819784, 978-1505819786

More Books

Students also viewed these Finance questions