You have been serving as Electroscan's project manager and are well along in the 29 In-store Scanner project. Develop a narrative status report for the

You have been serving as Electroscan's project manager and are well along in the 29 In-store Scanner project. Develop a narrative status report for the board of directors of the chain store that discusses the numbers of the project to date and at completion. Be as specific as you can using the numbers that you have been given. Remember that your audience is not familiar with the jargon used by project managers and computer software personnel so it needs to be translated into terms that they can understand. Your report will be evaluated on your detailed use of the data, your perspective of the current state and future status of the project and your recommendations. Permitted variances are within 10%. Any variations outside of that window require a corrective action plan. Actual Progress as of January 1 st (In thousands of dollars)

image text in transcribedimage text in transcribed
Name PV EV AC SV CV BAC EAC Scanner Project 430 405 476 -25 -71 915 1,128 H1.0 Hardware 92 88 72 -4 16 260 243 H1.1 Hardware Specifications 20 20 15 0 5 20 15 H1.2 Hardware Design 30 30 25 0 5 30 25 H1.3 Hardware Documentation 10 6 5 -4 10 8 H1.4 Prototypes 2 2 2 0 40 40 H1.5 Test Prototypes 0 0 0 0 0 30 30 H1.6 Order circuit boards 30 30 25 0 5 30 25 H1.7 Preproduction models 0 0 0 0 0 100 100 OP1.0 Operating System 195 150 196 -45 -46 330 480 OP1.1 Kernel Specifications 20 20 15 0 5 20 15 OP1.2 Drivers 45 55 76 10 -21 70 97 OP1.2.1 Disk Drivers 25 30 45 5 15 40 60 OP1.2.2 1/O Drivers 20 25 31 5 -6 30 37OP1.3 Code Software OP1.3.1 Code software OP1.3.2 Document software OP1.3.3 Code interfaces OP1.3.4 Beta test software U1.0 Utilities U1.1 Utilities specifications U1.2 Routing utilities U1.3 Complex utilities U1.4 Utilities documentation U1.5 Beta test utilities $1.0 System integration $1.1 Architecture decisions $1.2 Integration hard/soft $1.3 System hard/software test $1.4 Project documentation $1.5 Integration acceptance testing 130 30 45 55 97 20 30 30 17 46 25 12 75 20 30 25 118 20 30 60 105 40 25 40 148 15 35 90 60 45 99 -10 -15 -2 =11 15 240 100 50 60 30 200 20 20 100 20 40 125 10 50 20 15 30 368 200 42 96 30 260 15 35 150 20 40 145 75 20 12 30

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Planning And Control Techniques

Authors: Rory Burke

3rd Edition

047198762X, 9780471987628

More Books

Students also viewed these General Management questions

Question

2. Do not get drawn into I wont, you will arguments.

Answered: 1 week ago

Question

Do not get married, wait until I come, etc.

Answered: 1 week ago

Question

Do not come to the conclusion too quickly

Answered: 1 week ago

Question

Engage everyone in the dialogue

Answered: 1 week ago