15.2. A consulting firm is planning a reengineering project for a client. The following activities and time

Question:

15.2. A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified:

Activity Time, Days Immediate Predecessor A 1 —

B 2 —

C 2 —

D 2 A,B E 4 A,C F 1 C G 4 D H 8 G,E,F