Figure 5.5 gives task durations for software project activities. Assume that a serious, unanticipated setback occurs and

Question:

Figure 5.5 gives task durations for software project activities. Assume that a serious, unanticipated setback occurs and instead of taking 10 days, task T5 takes 40 days. Revise the activity chart accordingly, highlighting the new critical path. Draw up new bar charts showing how the project might be reorganised.

Step by Step Answer:

Related Book For  book-img-for-question

Software Engineering

ISBN: 9780321313799

8th Edition

Authors: Ian Sommerville

Question Posted: