=+ What are the implications? Estimated Days JOB PAINTING ASSEMBLY PACKING TOTAL TASK TIME DAYS UNTIL DUE
Question:
=+ What are the implications?
Estimated Days JOB PAINTING ASSEMBLY PACKING TOTAL TASK TIME DAYS UNTIL DUE A 1.5 2 0.5 4 15 B 4 3 1 8 16 C 3 2 0.5 5.5 8 D 6 4 1 11 20