You urgently need a sub-contractor to machine your free issue material. This is high-value, special steel. Your production director has asked you four questions:

1 What will the contract say about scrap management?

2 How will the issue and transportation of the free issue take place?

3 How will the capacity you require be guaranteed?

4 What happens if you cannot guarantee actual requirements other than on 24-hour notice?