You are managing the development of a case tracking system project for your large law firm. The
Question:
You are managing the development of a case tracking system project for your large law firm. The requirements phase of the project is almost complete, and preliminary design work has begun. The project is running several days behind schedule, which you don't consider serious, and it is within budget, but barely. Quality, in terms of requirements analysis, has generally been acceptable so far in your opinion, but some of the project team members have mentioned that they are not sure If certain issues have been fully resolved. Based upon this information, write a Project Progress Report, using the outline in Figure 411 as an example and following the guidelines described in Activity 7 in this chapter.
Step by Step Answer:
Systems Analysis And Design Methods
ISBN: 9780073052335
7th Edition
Authors: Jeffrey Whitten, Lonnie Bentley