The following costs have been estimated for the activities in a project: (a) Develop a cost schedule
Question:
The following costs have been estimated for the activities in a project:
(a) Develop a cost schedule based on earliest start times.
(b) Develop a cost schedule based on latest start times.
(c) Suppose that it has been determined that the $6,000 for activity G is not evenly spread over the three weeks. Instead, the cost for the first week is $4,000, and the cost is $1,000 per week for each of the last two weeks. Modify the cost schedule based on earliest start times to reflect thissituation.