Question: The Pickett Marketing Firm is developing a new Web-based media campaign for a client. The following table describes the relationships between the activities that need
The Pickett Marketing Firm is developing a new Web-based media campaign for a client. The following table describes the relationships between the activities that need to be completed.
.png)
(a) Develop a project network for this problem.
(b) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and the critical path(s).
IMMEDIATE PREDECESSORS TIME DAYS) ACTIVITY 10 E, F, G H, I
Step by Step Solution
3.41 Rating (167 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
718-M-S-L-P (1172).xlsx
300 KBs Excel File