The Precision Manufacturing Company is considering the purchase of an NC, machine and has narrowed the possible
Question:
Number of units in batch Probability
3 ..................0.1
6 ..................0.2
8 ..................0.3
14 ................0.4
18 ...................0.2
The distributions of the setup times and processing times for the two NC models follow. Assume that the work in batch shares a single setup and that each unit in the batch has equal processing time. Simulate two hours (or 10 batch arrivals) of operation for the two NC machines. Use the following random numbers the first one for the number of units in a batch, the second one for setup times, and the third one for run times:
(71 , 21 , 50) , (50 , 94 , 63) , ( 96 , 93 , 95) , (83 , 09 ,49) , (10 , 20 , 68) , (48 , 23 , 11) , (21 , 28 , 40) , (39 , 78 ,93) , (99 , 95 , 61) , (28 , 14 , 48)
Which one would you recommended if both machines cost the same to produce, operate, andmaintain?
Step by Step Answer:
Operations management processes and supply chain
ISBN: 978-0136065760
9th edition
Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra