You are the project manager of the software installation project in Table. You like to find the

Question:

You are the project manager of the software installation project in Table. You like to find the minimum cost schedule for your project. There is a $1,000 per week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week.

You are the project manager of the software installation project

a. What would be your target completion week?
b. How much would you save in total projects costs with yourschedule?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management processes and supply chain

ISBN: 978-0136065760

9th edition

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra

Question Posted: