An engineer analyzing cost data about hydrogen sulfide monitors discovered that the information for the first three
Question:
An engineer analyzing cost data about hydrogen sulfide monitors discovered that the information for the first three years was missing. However, he knew the cost in year 4 was $1250 and that it increased by 5% each year thereafter. If the same trend applied to the first three years, the cost in year 1 was:
a. $1312.50
b. $1190.48
c. $1028.38
d. $1079.80
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Basics Of Engineering Economy
ISBN: 9780073376356
2nd Edition
Authors: Leland T. Blank, Anthony Tarquin