MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2008 and was
Question:
MSK Construction Company contracted to construct a factory building for $525,000.
Construction started during 2008 and was completed in 2009. Information relating to the contract follows:
Required:
Record the preceding transactions in MSK’s books under the completed-contract and the percentage-of-completion methods. Determine amounts that will be reported on the balance sheet at the end of 2008.