10. is a method of scheduling that considers limited resources when creating a project schedule and includes...

Question:

10. is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.

a. Parkinson's Law

b. Murphy's Law

c. Cr~ical path analysis

d. Cr~ical chain scheduling