Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time
Question:
Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early fin- ish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time = 0). Which tasks are on the critical path? Highlight the critical path on your network diagram.