A finished good A consists of two child items, one B and one C. Lead time on

Question:

A finished good A consists of two child items, one B and one C. Lead time on each of these three items is 1 week, and 10 of each of these three items are available in inventory currently, available for use. How much of each item should be ordered and when should it be ordered, so that 50 A's might be finished in 3 weeks?