Posey Ceramics makes ceramic vases for a chain of department stores. The output and cost figures over

Question:

Posey Ceramics makes ceramic vases for a chain of department stores. The output and cost figures over the past four weeks are shown here. Labour costs $20 an hour, and materials are $8 per kilogram. Calculate the (a) labour productivity (in hrs), (b) material productivity (in kilograms), and (c) multifactor productivity for each week. Comment on the results.


Week 2 3 Units of output 4000 2000 5000 7000 No. of workers


2 Week Hours per week per 40 48 56 70 worker Material (kilograms) 128 256 324 450