For the case problem discussed in this chapter (Example 10.10), suppose that the requirements for RAM and

Question:

For the case problem discussed in this chapter (Example 10.10), suppose that the requirements for RAM and permanent storage are given by RAM Required Permanent Storage Activity (GB) Required (GB)

A 0 0 B 1.5 30 C 2.5 20 D 0.5 10 E 2.0 40 F 1.5 15 G 2.0 25 H 1.5 20 I 4.0 50

a. Determine the load profiles for RAM and permanent storage assuming that the activities are scheduled according to the Gantt chart of Figure 10–7.

b. Determine the load profiles for RAM and permanent storage assuming that the activities are scheduled according to the Gantt chart of Figure 10–19.