A project network has five pathsP1, P2, P3, P4 and P5. The total activity duration computed along
Question:
A project network has five paths—P1, P2, P3, P4 and P5. The total activity duration computed along each of these paths are—22, 31, 20, 30 and 19 days, respectively. What is the minimum duration for project completion?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction Project Management Theory And Practices
ISBN: 9789332542013
2nd Edition
Authors: Kumar Neeraj Jha
Question Posted: