The early occurrence time and the late occurrence time of the starting event of an activity are

Question:

The early occurrence time and the late occurrence time of the starting event of an activity are 10 and 12, respectively. The early occurrence time and the late occurrence time of the finishing event of the same activity are 22 and 26, respectively. If the estimated duration for the activity is 10 time units, what is the total float available for the activity?