In which type of contract arrangement is the contractor at the most risk of absorbing all cost

Question:

In which type of contract arrangement is the contractor at the most risk of absorbing all cost overruns?
A. Cost plus percentage of cost
B. Firm-fixed price
C. Time and materials
D. Cost-plus-incentive-fee