Using the data for Exercise 13.36, add the resource assignments to each of the activities and input
Question:
Using the data for Exercise 13.36, add the resource assignments to each of the activities and input their hourly rates as shown.
Construct an earned value chart for the project. Which activities have negative variances? What is the estimate at completion
(EAC) for the project? (Hint: Remember to click “Set baseline”
prior to creating the EVM table. This table is found by clicking on the “View” tab, then “Tables,” then “Other Tables.”)